Decarbonization program summary dashboard

Current Decarbonization Delivery KPI Status

2025 Performance
Quantitative KPI · In-year abatement, ktCO₂e
Score
2025 Target
70
Q3 Update
101
Expected score
2030 Target Delivery
Gate/Condition · residual emissions, MtCO₂e
2,383
4,547
2,164 MtCO₂e

Key Insights

Upstream is ahead of the 2025 target abatement due to extra CCUS initiatives identified in Q3 (subject to final year-end verification).

  • Upstream is on track to achieve 16 MtCO₂e residual emissions by 2030. It would require 38.6 MtCO₂e of abatement — 63% is realized and high confidence, 29% is medium confidence and 8% is low confidence/at risk.
  • Delivery requires $3.1Bn Capex, of which $2.0Bn is in the business plan.
  • Offshore electrification (3.2 MtCO₂e, low confidence) is the main initiative at risk — FEED sign-off is in progress and needed before Q3 to stay on the 2030 pathway.

Decarbonization Program Summary

Million tCO₂e

CAPEX

Committed Planned / At risk
Confidence Level Abatement(MtCO₂e) 2026–2030 Capex($mn)